ACFS Port Logistics warehouse demolition project overview
The ACFS Port Logistics warehouse demolition at the Port of Melbourne involved a large, steel-framed structure with concrete footings and asbestos cement roofing and wall cladding. Originally used as a combination employee carpark and quarantine inspection facility for the Australian Federal Biosecurity sector, the building had deteriorated significantly due to ground level subsidence.
Also within scope were two adjoining timber-framed structures, also in poor condition, located under the warehouse awning at its south-western corner, as well as two 30-metre steel lighting tower poles on the northern elevation.
Industrial Demolition Services (IDS) had previously delivered shed demolition works for Patricks in the Port of Melbourne area, providing relevant local knowledge and operational familiarity coming into this project.
Scope of work
- Site establishment and enabling works
- Underground service location and isolation of all services within the project footprint
- Soil investigation
- Removal of hazardous building materials
- Demolition of the ACFS warehouse, quarantine shed and blue shed
- Loadout, recycling and disposal of demolition materials
- Final clean-up and handover to client
Specialist services required: Marine Demolition | Hazardous Materials | Industrial Demolition
Unique challenges
Working in a live site
Three distinct challenges emerged during this warehouse demolition project. The first was the continuous movement of mobile plant on the active port site. ACFS trucks and reach stackers operated throughout the demolition, requiring careful management of exclusion zones and personnel movement at all times.
Container safety risk
The second was a container orientation issue. Rows of 40ft containers were stacked parallel to the working area. ACFS had previously experienced a toppling incident at another site with containers in this configuration. This posed a genuine safety risk that required an ongoing operational response rather than a one-time fix.
Hazardous materials risk
The third challenge was an unexpected hazardous materials find. Blocked downpipes and gutters had resulted in a build-up of debris that, on testing, was confirmed to contain asbestos. This material had not been identified in the original scope and required a new removal methodology to be developed.
Solutions
Mandatory exclusion zone
To manage the live port environment, IDS incorporated a mandatory 10-metre exclusion zone from the reach stackers. This was communicated to all personnel at site induction. Temporary fencing was erected 10 metres beyond the warehouse perimeter to enforce the zone throughout the works.
Immediate stop-work policy
To mitigate the container safety risk, IDS maintained close and regular communication with ACFS operations throughout the project. Any containers moved into or placed near the active work area triggered an immediate work stop, with both parties coordinating to reposition them safely before works resumed.
Bespoke asbestos removal methodology
For the unexpected asbestos in the gutters, IDS worked closely with the on-site hygienist and a licensed asbestos removal crew to develop a bespoke removal methodology. A telehandler fitted with a bucket attachment was positioned to catch falling material from below, while asbestos removalists working from an elevated work platform oxy-cut individual gutter sections free. The bucket attachment captured all dislodged material directly, minimising the risk of fibre release and protecting both workers and the surrounding site.
Outcomes
The ACFS warehouse demolition was completed with the majority of works delivered on programme. The exception was the unexpected asbestos found in the gutters, which extended the duration of that scope due to the complexity of the removal methodology and the need to follow a safe work approach as directed by the on-site hygienist.
Demolition material recovered from site totalled 637.46 tonnes, comprising 307.40 tonnes of steel, 153.20 tonnes of concrete, brick and asphalt, 143.36 tonnes of asbestos, and 33.50 tonnes of general waste.
Three safety incidents were recorded during the project: personnel observed working at height without fall protection in place; a hydraulic oil tank filled with diesel in error; and shipping containers staged in an incorrect orientation posing a risk to on-site personnel. Each incident was managed and resolved in accordance with IDS safety procedures.
The site is now in active use as a container storage yard for ACFS’s fleet of 20ft and 40ft shipping containers.