Project overview
Industrial Demolition Services (IDS) successfully completed the demolition of several redundant structures and associated plant equipment at the Sibelco Charbon Lime Plant, located in New South Wales.
The client required the removal of obsolete infrastructure to make way for critical upgrades to their dust management systems and plant operations team.
Scope of work
- Demolition of raw feed bins, steam economisers, boilers, exhaust stacks, and silos
- Controlled structural collapses at heights exceeding 20 metres
- Removal of laboratory and compressor buildings, No. 3 boiler, related dust systems, and silos
Specialist services required: Decommissioning | Hazardous Materials | Industrial Demolition
Unique challenges
This project posed several unique challenges. The most significant aspect was the need to carry out demolition at substantial elevations, with some structures exceeding 20 metres in height. This elevated the complexity of safety and logistical requirements, requiring meticulous planning for crane lifts and controlled collapses.
Additionally, the presence of friable asbestos presented environmental and health risks, requiring specialist management. A further challenge was the requirement to complete the first two stages of demolition while the Sibelco Charbon Lime Plant remained operational. Ensuring the project’s progress while minimising disruptions to ongoing production demanded precise scheduling and close cooperation with the Sibelco.
Solutions
To address these challenges, IDS deployed an experienced project team, with a dedicated project manager leading the works. Detailed planning and risk assessments were conducted to ensure the safe execution of high-risk tasks, including crane lifts and controlled collapses.
Demolition works were carefully planned around Sibelco’s production schedule to maintain plant operations during the initial stages. By coordinating key activities during quieter periods of the plant’s operations, IDS was able to minimise disruptions.
Outcome
The project was completed on time and within budget, with all safety and environmental standards adhered to. The successful demolition of the redundant structures enabled Sibelco to proceed with their facility upgrades without major interruptions to their operations.