Location: Mentone, Victoria
    Duration: March 2020

    Level Crossing Removal Mentone Station | Montmorency Station | Diamond Creek Station | Southern Program Alliance

    Project overview

    Mentone Station needed to be relocated, as part of the Level Crossing Removal Program, so site works could proceed. Industrial Demolition Services (IDS) was contracted by SPA (comprised of Lendlease, Acciona, Coleman Rail, WSP, Metro Trains Melbourne, and Level Crossing Removal Program) to present a proposal.

    The proposal required sign-off from Heritage Council Victoria as the landmark 100-year-old Mentone Down Track Station Building is listed on the Victorian Heritage Register.

    Scope of work

    IDS undertook the project to move the building to temporary storage to make way for piling work required for a new underground station.

    The work was to be completed within a timeframe where:

    • the occupation period was 2 weeks
    • trains would be discontinued for 5 days only

    Specialist services required:   Transport  |  Urban Renewal  | Government

    Unique challenges

    Moving a heritage building suffering significant deterioration provided a unique set of challenges. Standard industry practice for historic high-profile buildings is to deconstruct the building piece by piece, then store the pieces for subsequent reconstruction.

    In this instance the standard approach was not feasible. The time required for this method exceeded the occupation window. Furthermore, accurate reconstruction of such an aged building in its entirety provided additional challenges.

    An innovative “outside the box” approach was needed. The solution would need stretch the boundaries of standard industry practices. Sign-off by Heritage Victoria was required for the proposal to be successful.

    Solutions

    The solution was to lift the entire building as a whole. This approach required extensive review of the existing structure. Detailed calculations of the building weights and structural analysis for lifting frame, including loads during the lifting operation, was required. Based on these calculations, a design was formulated, then reviewed and approved by an independent 3rd party structural engineer.

    Laminated veneer lumbers (LVL’s) were introduced into the structural makeup of the building and screwed onto each wall stud externally to provide diagonal bracing. This was to minimise lateral and torsional stresses encountered during lifting.

    Two perimeter frames comprising of PFC’s (Parallel Flange Channel’s) were attached to each wall stud at the top and bottom to increase the stability of the structure during lift. Universal Beams (UB’s) and lifting points were introduced underneath the bottom PFC which also provided a support for the lifting frame.

    Sections with significant rot were identified and repaired or excluded, depending on their location within the structure. With the preparation work complete the building was separated from its base and a 250 Ton crane relocated the building to its new position.

    Outcome

    The Level Crossing Removal works were able to proceed with the Mentone Station successfully relocated within the occupation window (and time to spare). No damage was identified during the lift.

    IDS delivered on all fronts with pinpoint accuracy, to the satisfaction of both the Southern Program Alliance (SPA) and Heritage Victoria.