Location: Watsonia, Victoria
    Duration: 1 October – 10 October 2025

    IDS partnered with Acciona on the Grimshaw Street Bridge demolition project.

    Grimshaw Street Interchange: bridge removal project overview

    Industrial Demolition Services (IDS) was engaged by Acciona to undertake the demolition of the Grimshaw Street bridge, as part of the interchange upgrade in Greensborough, Victoria. The bridge formed part of critical infrastructure within the broader North East Link (NEL) upgrade works, which will expand transport capacity by accommodating additional rail tracks and increased vehicle movements.

    The existing bridge structure, approximately 30 metres in length, was comprised of concrete abutments, steel deck beams and a concrete slab poured over supporting beams. Live rail tracks operating beneath the bridge remained active throughout the occupation, requiring careful planning and protection measures during demolition activities.

    Despite being in fair structural condition with minimal deterioration over its service life, the bridge was nominated for removal to facilitate construction of a new, expanded structure.

    IDS has previously delivered demolition works for Acciona and brought proven experience in complex infrastructure demolition within live environments to this project. All works were carefully coordinated to align with occupation timeframes and live rail safety requirements.

    Scope of work

    The scope of works included:

    • Delivery and mobilisation of plant and equipment
    • Site establishment and enabling works
    • Installation of track protection measures, including ballast protection
    • Removal of asphalt and crushed rock surfaces
    • Demolition of the concrete bridge deck
    • Demolition of abutment and wing walls
    • Processing and load-out of demolition materials
    • Bulk excavation behind existing abutments
    • Final site clean-up and handover to the client

    Specialist services required:  Demolition  |  Specialist Demolition  |  Recycling

    Unique challenges

    Demolishing the bridge at the Grimshaw Street Interchange presented several technical and logistical challenges.

    Live rail environment
    The bridge was positioned directly above an operational rail corridor, introducing significant safety and coordination risks. Train movements beneath the structure required strict compliance with rail safety protocols and engineered protection systems.

    Occupation time constraints
    Due to program urgency and strict shutdown windows, demolition activities were undertaken within a tightly controlled occupation period. All works needed to be executed efficiently to avoid disruption to rail operations and surrounding infrastructure works.

    Heavy crane lifts
    Cranage formed a critical component of the demolition methodology. The largest lift during the project reached 60 tonnes, with critical operations supported by an 800-tonne crane. All lift calculations were engineered and verified, with estimated weights falling within 1% of actual recorded weights. Lift studies were third-party engineered and completed in consultation with the client and crane subcontractor.

    Solutions

    IDS implemented a detailed and methodical approach to ensure safe and efficient project delivery.

    For works over the live rail corridor, all IDS personnel and subcontractors completed required onboarding, inductions and competency verification. Comprehensive risk reviews were undertaken to ensure all team members understood site-specific hazards and rail safety requirements.

    To manage the restricted occupation timeframe, IDS worked closely with the client to develop a detailed hour-by-hour demolition program. This ensured every task was sequenced, resourced and accounted for, enabling works to proceed without delay.

    For crane operations, IDS collaborated closely with the crane subcontractor to engineer all lifts. Detailed weight calculations, crane positioning plans and designated drop zones were developed in advance. This planning ensured safe execution of all heavy lifts and seamless coordination on site.


    Outcome

    The Grimshaw Bridge demolition was successfully delivered on time and within budget – in line with project objectives and infrastructure program requirements. Through careful planning, engineered lifting methodologies and strong collaboration with the client and subcontractors, IDS safely demolished the existing bridge structure, including:

    • 25 tonnes of general waste removed
    • 200 tonnes of scrap steel processed for recycling
    • 1,500 tonnes of concrete removed
    • 2,000 tonnes of soil excavated