Project overview
Industrial Demolition Services (IDS) undertook the decommissioning of the BOC Helium Plant, Darwin, in 2024. The project required the extraction, preservation, and overseas export of many key plant items, including equipment and infrastructure. BOC, part of Linde Group, is the largest supplier of industrial, medical, and specialty gases in the South Pacific.
The BOC Helium Plant, established in 2010, was the first helium plant in the Southern Hemisphere. This venture positioned Darwin and Australia as significant contributors to the global helium supply. Situated next to Darwin LNG (operated by Santos), the plant produced approximately 150 million cubic feet of helium annually—enough to meet Australia’s demand with surplus for export.
The plant ceased operations in 2023 due to the depletion of Santos’s Bayu-Undan gas field, which supplied its feedstock gas.
Scope of work
- Isolating and decommissioning the plant’s services.
- Identifying and preserving all equipment and infrastructure for sea freight.
- Specialist packing of all items – as per the preservation plan
- Internal bracing of specialised helium & nitrogen vessels
- Extracting and transporting salvageable items to the Port of Darwin.
- Demolishing the plant buildings, concrete slabs, and footings.
- Recycling and crushing concrete for reuse onsite.
- Grading the site to minimise waterlogging and erosion risks.
Specialist services required: Decommissioning | Hazardous Materials | Industrial Demolition
Unique challenges
This was a highly specialised and tightly sequenced project that required experienced personnel, forward planning and a strong problem-solving mindset.
One of the most complex elements was implementing the preservation plan. A large number of equipment and infrastructure items were identified for salvage. Many of these were custom built and required purpose-designed tooling and confined space entry to remove safely. Coordinating the extraction, documentation and packing of these items to meet export requirements involved specialist teams and close liaison with the client.
The project also involved isolating the high-voltage power supply, which was shared with the neighbouring Santos-operated LNG facility. This could only occur during LNG shutdowns, requiring careful scheduling and agreement between all parties, including Santos, the HV contractor, the utility provider and BOC, to avoid disruptions and maintain site safety.
The site’s location added further complexity. With demolition works taking place alongside an operating LNG plant, strict environmental controls were enforced to manage risks such as noise, dust, vibration and spills.
All works had to be completed before the onset of Darwin’s storm season, leaving little margin for delay. Once salvage operations were complete, demolition of the plant structures and slab removal proceeded, followed by a series of groundworks to reduce the risk of erosion or waterlogging from extreme weather events.
Solutions
Specialist personnel
The project demanded a team of experienced personnel to handle its specialised requirements. IDS developed a detailed project schedule, issuing weekly status updates and holding twice-daily meetings with BOC in Darwin to ensure progress remained on track. This proactive communication helped identify and mitigate potential delays before they could impact the timeline.
Before initiating the preservation plan, IDS isolated and tagged the plant’s salvageable items, depressurised process gases, drained oil from chambers, and removed catalysts such as perlite, palladium, charcoal, and molsieve. A thorough review of engineering drawings enabled the team to identify and isolate the necessary helium plant and equipment items.
Custom equipment
To execute the work, IDS relied on state-of-the-art tools, including custom-built equipment to handle specialised tasks such as catalyst removal from helium equipment. For instance, custom-built blind flanges, gauges, and valves were manufactured to suit the helium equipment, which was originally produced overseas. Nitrogen blanketing was applied to maintain a stable pressure of two bars within the helium equipment, preventing damage from excess pressure.
Specialised fabrication was required to address the unique specifications of the helium and nitrogen vessels, which were constructed abroad. IDS used German engineering drawings to fabricate the necessary part s and internal bracing for these vessels. All work involving these vessels adhered to confined space entry protocols.
Tailored packing for export
Salvage items were meticulously sorted, documented, and packed. Smaller components were placed into custom-built marine-grade crates for export, while larger items required a tailored approach.
For the larger helium and nitrogen vessels, IDS teams entered confined spaces to install internal bracing for pipes, securing them to the vessel shells to prevent damage during transport. Custom-built saddles were then used to safely transport these vessels.
Multiple cranes operated simultaneously to extract and load the plant’s components, with some requiring dual lifts due to their size, such as the largest vessel weighing 45 tons and measuring 20 meters long and 3 meters wide.
All items were thoroughly cleaned to meet border control requirements before leaving the site. The packing process followed a detailed list with tagged items, ensuring accuracy and compliance. After preparation, the salvaged materials were carefully transported to the Port of Darwin for overseas distribution.
Site preparation
Throughout the project, IDS maintained open communication with the neighbouring LNG Plant to provide updates and ensure no disruptions occurred. Once the salvage operations were complete, the demolition phase began. IDS dismantled the plant buildings and removed the foundation slab and footings, processing approximately 4,000 tons of concrete.
The crushed material was reused onsite to backfill the resulting void. The site was then graded and levelled to allow for proper water runoff into nearby stormwater drains, minimising the risk of water logging or erosion.
Outcome
Industrial Demolition Services comprehensive approach ensured the BOC Helium Plant decommissioning project was delivered efficiently and met all client requirements. The project was delivered ahead of schedule, within budget and met all BOC’s expectations. All salvageable items were successfully preserved, documented, and transported to the Port of Darwin for export.